01 Sep Roadworks – September 5 to 8, 2023
Ali Excavation will carry out pavement preparation work (pulverizing and levelling) and paving from September 5 to 8. The schedule of work is below...
Ali Excavation will carry out pavement preparation work (pulverizing and levelling) and paving from September 5 to 8. The schedule of work is below...
Ali Excavation will be carrying out pavement preparation work (pulverization and levelling) on the following streets from August 29th to September 1st...
Cameron will be closed between 75 Cameron and Saint-Jean from 6 am to 1 pm on Thursday, July 13th...
Work on the guardrails on Main Road near the corner of Bellevue is scheduled for this Thursday, July 6, 2023, starting at 7:00 am...
The lines in the public parking lots and parking spaces will be painted during the night this week....
Roadworks for the week of June 19, 2023...
Main Road, between Quarry Point and Bellevue, will be closed to all except local traffic. Traffic flow will be on alternating lanes, with signalers on site. Expect a wait time of approximately 15 minutes .....
Residents and visitors to Hudson are strongly advised to avoid the construction zone on Main Road between Quarry Point and Bellevue on June 8th and 9th....
Residents and visitors to Hudson are strongly advised to avoid the construction zone on Main Road between Quarry Point and Bellevue next week...
Full closure of Main Road between Parsons and Bellevue as the road surface is prepared for paving...