Roadworks – September 5 to 8, 2023

Ali Excavation will carry out pavement preparation work (pulverizing and levelling) and paving from September 5 to 8. The schedule of work is below:

Monday, September 4: No work on Labour Day.

Tuesday, September 5 :

  • PINE: Pulverizing and levelling of the roadbed.
    • Closed between Ridge and 126 Pine,
    • Local traffic only, with the possibility of a several-minute wait.
  • BLENKINSHIP: Pulverizing and levelling of the roadbed.
    • Closed between Main and the entrance to St-Thomas Park,
    • Local traffic only, with the possibility of a several-minute wait.

Wednesday, September 6:

  • WINDCREST: Paving.
    • Complete closure between Westwood and Cavagnal, and on Cavagnal opposite #165 and #166,
    • Mobile work with complete closure,
    • Residents will be able to access the area as directed by signalers,
    • There is a possibility of a detour,
    • Anticipate a wait time of approximately 45 minutes when the asphalt is being applied in front of each driveway.

Thursday, September 7 :

  • BUTTERNUT: Pulverizing and levelling of the roadbed.
    • Closure between Main Road and Turtle Pond and on the portion of Turtle Pond south of Butternut,
    • Local traffic only, with the possibility of a several-minute wait.
  • STIRLING: Paving.
    • Complete closure between côte Saint-Charles and Windcrest,
    • Mobile work with complete closure,
    • Residents will be able to access the area as directed by signalers.
    • There is a possibility of a detour,
    • Anticipate a wait time of approximately 45 minutes when the asphalt is being applied in front of each driveway.

Friday, September 8 :

  • BUTTERNUT: Pulverizing and levelling work continues.
    • Closure between Main Road and Turtle Pond and on the portion of Turtle Pond south of Butternut,
    • Local traffic only, with the possibility of a several-minute wait.