Major Roadworks – October 24 to 28, 2022

Due to extensive roadwork the week of October 24, 2022, residents are strongly advised to avoid:

  • Main Road, between Quarry Point and Bellevue, between 7:00 a.m. and 7:00 p.m., Monday, October 24 through Friday, October 28. Access to Main Road will be very limited and subject to closures and detours.
  • Wharf Road from Monday, October 24 to Friday, October 28; complete closure of the level crossing. A detour will be put in place on Yacht Club Road to access Jack Layton Park.
  • Yacht Club Road on Thursday, October 27, between 9 a.m. and noon.

Here are the details :

Monday, October 24th :

  • Replacement of catch basins and pipes in front of 260 Main Road; complete closure.
  • Replacement of longitudinal culvert west of Royal Oak Street; complete closure, emergency vehicle access or collection vehicles only.
  • Replacement of longitudinal culvert in front of 229 Main Road; complete closure, emergency vehicle access or collection vehicles only.
  • EXO to perform work on the Wharf Road level crossing. Complete closure of the level crossing, detour via Yacht Club Road to access Jack Layton Park.
  • Flushing of the aqueduct network.
  • Reprofiling of the ditch at 112 Mount Pleasant.
  • Removal of the floating dock at Jack Layton Park.

Tuesday, October 25th :

  • Replacement of the cross culvert near 219 Main Road; complete closure.
  • Replacement of longitudinal culvert between 171 Main Road and 169 Main Road; complete closure, emergency vehicle access or collection only.
  • Work on the Wharf Road level crossing. Complete closure of the crossing, detour via Yacht Club Street to access Jack Layton Park.
  • Flushing of the aqueduct network.
  • Reprofiling of the ditch at 112 Mount Pleasant.
  • Removal of pedestrian lane posts on Bellevue.
  • Removal of speed bumps on Cambridge and Mayfair Streets.

Wednesday, October 26th :

  • Widening of Main Road from 322 Main Road to Bellevue; complete closure, access for emergency vehicles or collection only.
  • Work on the Wharf Road level crossing. Complete closure of the crossing, detour via Yacht Club Street to access Jack Layton Park.
  • Flushing of the aqueduct network.
  • Removal of pedestrian lane posts on Bellevue.
  • Removal of speed bumps on Cambridge and Mayfair Streets.

Thursday, October 27th :

  • Widening of Main Road from 333 Main Road; complete closure, access for emergency vehicles or collection only.
  • Work on the Wharf Road level crossing. Complete closure of the crossing, detour via Yacht Club Street to access Jack Layton Park.
  • Complete closure of Yacht Club Road for 30 minutes between 9:00 a.m. and noon to offload equipment needed for EXO work.
  • Flushing of the aqueduct network.
  • Removal of pedestrian lane posts on Bellevue.
  • Removal of speed bumps on Cambridge and Mayfair Streets.

Friday, October 28th :

  • Widening of Main Road from 333 Main Road; complete closure, access for emergency vehicles or collection only.
  • Work on the Wharf Road level crossing. Complete closure of the crossing, detour via Yacht Club Street to access Jack Layton Park.
  • Flushing of the aqueduct network.

The contractor will advise residents prior to undertaking the work on the access culverts.
Main Road will be open between 7 p.m. and 7 a.m.
Please note that the work of our contractor Ali Excavation Inc. is subject to change without notice.
The contractor has committed to updating the addresses on the signs indicating the closed areas on a daily basis.