Paving operations: July 10 to 19, 2024

Ali Excavation will begin work on the following street sections on Wednesday, July 10th (weather permitting)During these operations, expect occasional delays, with alternating traffic when necessary.

  • McMartin, from Evergreen to the end of the street.
  • Carmel, from #28 to the intersection of Windcrest.
  • McNaughten, from Main Road to St Jean (excluding the public parking spaces).
  • Quarry Point, from Main Road to #51.
  • Reid, from Main Road to the end of the street.
  • Cedar, from Lakeview to #64.

ORDER OF WORK:

  • July 10-11-12: Surface preparation; grinding and compacting of the road surface.
  • July 15–19: Paving operations.
  • All works are weather dependent.

IMPORTANT RESTRICTIONS:

    • Between July 10–12 and July 15–19, residents, visitors, contractors, etc. will be unable to park on the affected streets. Plan ahead and let your contractors/service providers know.
    • During paving operations, expect delays to enter and exit your driveway entrance.
    • Please drive with caution and respect all signage in place to ensure the safety of personnel working on this project.