LAKEVIEW 2025
This full reconstruction—from underground infrastructure to a new road surface—represents a major investment in our town’s future.
This full reconstruction—from underground infrastructure to a new road surface—represents a major investment in our town’s future.
Watch the video
Consult the presentation
Consult the project plan
We are pleased to announce that the foundation and excavation work, along with the installation of drainage infrastructure and retention basins along Lakeview, is now complete. This marks an important milestone in the project and brings us one step closer to its completion.
In the coming two weeks, grading, leveling, and possibly paving will be carried out on Lakeview, from Selkirk to Oakland. Work on landscaping and paving the multi-purpose path between McNaughten and Selkirk is continuing. Please be aware that all work is subject to weather conditions.
Selkirk to McNaughten
Paving and landscaping operations continue.
Selkirk to Oakland
Grading and levelling in preparation for paving.
Street and intersection closures
Expect temporary restrictions, especially during paving operations.
The work planned includes: removing asphalt at the Oakland/Lakeview intersection, foundation work between Selkirk and Oakland, and paving along both the multi-purpose path and Lakeview. Crews will also be planting trees and shrubs within the Town right-of-way. Please note that a second layer of asphalt will be applied on Lakeview next spring, after the freeze-thaw cycle.
Selkirk to McNaughten
Paving operations continue.
Selkirk to Oakland
• Excavation and foundation work continue from Maple to Oakland.
• One (1) water service connection will be done on Monday morning. Anticipate cloudy or brownish water in the area from Selkirk to Oakland.
Street closures
The following section of Lakeview will be closed:
• Elm to Oakland
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
• Elm and Lakeview; and
• Oakland and Lakeview.
Due to weather delays, paving of the multi-purpose path between Selkirk and McNaughten is now planned for the week of September 29. Excavation work will continue through to Oakland.
Selkirk to McNaughten
Paving of the multi-purpose path.
Selkirk to Oakland
• Excavation continues from Maple to Oakland.
• Storm sewer and water service connections will be done as the excavation advances. Anticipate cloudy or brownish water in the area from Selkirk to Oakland.
Street closures
The following section of Lakeview will be closed:
• Maple to Oakland;
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
• Maple and Lakeview; and
• Elm and Lakeview.
The project continues to move rapidly, with work planned along the entirety of Lakeview, from McNaughten to Elm.
Selkirk to McNaughten
Final levelling and paving of the multi-purpose path.
Selkirk to Oakland
• Excavation continues from Hazelwood to Elm.
• Storm sewer and water service connections will be done as the excavation advances. Anticipate discoloured water in the area from Selkirk to Oakland.
Street closures
The following section of Lakeview will be closed:
• Hazelwood to Elm;
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
• Hazelwood and Lakeview;
• Maple and Lakeview; and
• Elm and Lakeview.
The project will evolve rapidly over the next two weeks, with work planned along the entirety of Lakeview, from McNaughten to Oakland.
NOTICE: The intersection of Cameron and Lakeview will be completely closed at some point during the week of September 15th. Traffic will be detoured along adjacent streets.
Selkirk to McNaughten (including the intersection of Cameron)
• Monday to Wednesday: grading and levelling
• Thursday to Friday: paving operations will take place, barring any unforeseen delays or poor weather conditions. Expect delays of up to 45 minutes to enter or access your driveway. Access to this section of Lakeview will be restricted.
Selkirk to Oakland
• Monday to Friday: Excavation continues from Maple to Oakland with the addition of a second excavation team.
• Storm sewer and water service connections will be done as the excavation advances. Anticipate discoloured water in the area from Selkirk to Oakland.
Street closures
The following sections along Lakeview will be closed:
• Selkirk to Hazelwood;
• Cameron to Melrose; and
• Cameron to McNaughten.
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
• Selkirk and Lakeview;
• Hazelwood and Lakeview; and
• Cameron and Lakeview.
Discoloured water
IMPORTANT NOTICE:
The intersection of Cameron and Lakeview will be partially closed the week of September 8th. Alternating traffic will be allowed; flag-persons will be on site to manage the traffic
Storm sewer and water service connection work
Street closures
The following street sections on Lakeview will be closed:
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
Discoloured water
IMPORTANT NOTICE:
The intersection of Cameron and Lakeview will be partially closed the weeks of September 2nd and September 8th. Alternating traffic will be allowed; flag-persons will be on site to manage the traffic
Storm sewer and water service connection work
Street closures
The following street sections on Lakeview will be closed:
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
Discoloured water
Storm sewer and water service connection work
Discoloured water
Street closures
The following street sections on Lakeview will be closed:
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
Storm sewer and water service connection work
Roadwork
Other infrastructure work
Street closures
The following street sections on Lakeview will be closed to all but local traffic:
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
Storm sewer and water service connection work
Roadwork
Other infrastructure work
Excavation for the multi-use path infrastructure and drainage basin.
Street closures
The following street sections on Lakeview will be closed to all but local traffic:
Intersection closures
The following intersections may be fully or partially closed. Please respect the signage in place:
Boil-Water Advisory
Residents living along Lakeview between Hazelwood and Maple streets should anticipate receiving a hand-delivered preventive boil-water advisory once the fire hydrant has been relocated. Expect the advisory to last approximately 72 hours. A hand-delivered notice will be distributed as soon as the advisory is lifted.
Closures
The following intersections may be fully or partially closed. Please respect the signage in place:
The Reconstruction Phase begins in Zone 1
The majority of vegetation designated for removal between Selkirk and McNaughten has been cleared.
A site inspection to identify and mark trees and vegetation for removal along Lakeview’s western section, from Selkirk to Oakland, is scheduled for the week of July 21.
A reminder that the Lakeview project has been divided into two zones, with Selkirk as the lowest drainage point:
• Zone 1: to the east, from Selkirk to McNaughten; and
• Zone 2: to the west, Selkirk to Oakland.
Planned Work Starting Monday, July 14 (Zone 1: Selkirk to McNaughten)
1. Ongoing extension of the sewer network at the intersections of Selkirk, Pine, Cedar and Melrose;
2. Removal of the asphalt between Selkirk and Pine; and
3. Relocation of the fire hydrant at the corner of Pine and Lakeview.
Boil-Water Advisory: Residents living in the area of Pine and Lakeview should anticipate receiving a hand-delivered preventive boil-water advisory once the fire hydrant has been relocated. Expect the advisory to last approximately 72 hours. A hand-delivered notice will be distributed as soon as the advisory is lifted.
Closures
Fully Closed Intersection: Selkirk & Lakeview
Partially Closed Intersections (south side):
Collections
Garbage, recycling, compost, and bulky items will be collected between 5 a.m. and 7 a.m. in the area bordered by Main Road, Oakland, and Cameron on the regular collection day for the duration of the project, scheduled to end on October 31, 2025.
Please place your bins at the end of your driveway the night before.
Removal of vegetation in Zone 1 (Selkirk to McNaughten) to begin
On July 2nd, the Town’s Environment Technician along with the Landscape Architect, and Civil Engineers hired for the project, conducted a site inspection along the eastern portion of Lakeview from Selkirk to McNaughten. The objective of this inspection was to identify and mark the vegetation and trees for removal. During this inspection five (5) trees previously slated for removal were identified as being possible to conserve using specialized excavation methods with hydro-excavation rather than traditional mechanical equipment. These trees include two (2) Norway Maples, one (1) Silver Maple, one (1) Oak, and one (1) Fir.
The inspection along the western portion of the Lakeview project, from Selkirk to Oakland is planned to take place in the coming weeks.
The Lakeview project has been divided into two zones of Selkirk as the lowest drainage point:
Zone 1: to the east, from Selkirk to McNaughten
Zone 2: to the west, Selkirk to Oakland
The Construction preparation phase will continue during the week of July 7, 2025 in Zone 1 (Selkirk to McNaughten) and includes the following activities:
1. Removal and trimming of identified trees and vegetation:
a. Trees marked with a red dot will have their branches trimmed to prevent damage during construction. This work will be performed by a certified arborist;
b. Trees marked with a red “TH” will be removed;
c. Hedges, partial hedges, smaller trees, and other vegetation located within the public right of way will also be removed.
2. Exploratory excavation for grading;
3. Extension of the sanitary sewer network at the intersections of Selkirk, Pine, Cedar and Melrose streets;
4. Installation of worksite signage; and
5. Mobilization of equipment and materials.
Additionally, a temporary watermain will be installed on the south side of Lakeview between Maple and Melrose streets. This will serve as an emergency water source should water service need to be interrupted during construction. Please note that throughout the construction phase, water will be available in the mornings, evenings, and overnight. Any planned daytime water shutdowns will be communicated in advance to allow sufficient preparation time.
Identification of vegetation to be removed begins on July 2
The final preparations prior to the excavation phase continue during the week of June 30th and include:
| Description | Start Date |
| Camera inspections:
Video recordings will be made of properties and three sides of each building along Lakeview. This documentation serves as a “before” record prior to excavation and helps protect property owners in the event that construction work causes any damage. |
On-going |
| Exploratory excavation for grading | June 30 |
| Identification and marking of the vegetation to be removed
Our Environment Technician, Landscape Architect, and a representative from Shellex will be walking the site to identify all vegetation and trees slated for removal. |
July 2 |
All work will be carried out on weekdays between 7:00 a.m. and 6:00 p.m.
The excavation phase is scheduled to begin on July 14.
Due to its advanced state of deterioration, Lakeview Street must be completely rebuilt. We are also required to upgrade the drainage system to meet current environmental standards.
To enhance pedestrian safety, a *multi-use path will be added on the north side (river side). This path will be 2.5 metres wide (1 metre narrower than a bike path), with a 1-metre planting/drainage strip separating it from the street.
The path will extend to Oakland and to McNaughten and connect to existing paths that lead to Westwood Senior and St. Thomas schools.
The total width of Lakeview (including the path) will be increased from 6.5m to 11m (21.5 to 36 feet).
Speedbumps will be installed at all intersections that do not have stop signs.
Sump pump pipes for properties along the south side of Lakeview will be connected to the new drainage system, removing the need for ditches.
Benches and trash cans will be installed in 6 locations along the new path.
Total investment: $4 million
Investment to date: $803,475
To reduce the financial burden on taxpayers, 50% of the cost of this project will be financed by a $2.04 million Federal Government grant.
The path itself, which is a condition of the grant, is expected to cost approximately $250K.
To make room for the multi-use path, the Town will use the Town right-of-way (property owned by the Town outside of the property lines). This means:
In some cases, vegetation or structures located in the municipal right-of-way (outside of the property lines) will be removed.
Trees that are dead, dying, or that will become hazardous due to excavation work required for the project will be removed. To offset this, at least two new trees will be planted for every tree that is cut. In addition, five high-value trees have been identified for conservation and will be protected throughout the project.
Individual meetings with property owners affected by the project have begun to explain the impacts and to propose solutions to replace what will be removed.
Mature plants and trees will be used as replacement plantings. A landscape architect will also be hired to review the existing plans and to suggest improvements.
What is a multi-use path?
It is a designated pathway intended to safely accommodate multiple types of non-motorized users. This typically includes:
2021
2022
2023
2024