Resurfacing operations on Main Road, Monday Sept 10th to Friday Sept 14th 2018, weather permitting

Resurfacing operations on Main Road, Monday Sept 10th to Friday Sept 14th 2018, weather permitting

Resurfacing operations will be done from 7 am to 5 pm throughout the week of September 10th 2018 on Main Road, between 656 Main Road and 754 Main Road, weather permitting.

Schedule:

MONDAY, SEPTEMBER 10th:

  • Resurfacing between 656 Main Road and the railroad crossing: the work will be done in alternate directions to allow for traffic flow.

TUESDAY, SEPTEMBER 11th:

  • No resurfacing operations

WEDNESDAY, SEPTEMBER 12th through FRIDAY SEPTEMBER 14th:

  • Resurfacing between the railroad crossing and 754 Main Road: the work will be done in alternate directions to allow for traffic flow.

Residents might experience significant wait times before exiting and entering their driveways as paving operations cannot be halted while asphalt is being laid.

In addition, a cooling time of a minimum of 30 minutes is required before vehicles can roll on the newly paved surface.  

No parking is permitted on this part of Main Road during paving operations.